Membrane method in assessment of organizational and technical reliability of NPP construction projects

Main Article Content

Denis Evgenievich Sezemin

Abstract

The materials of the presented research paper are based on the analysis of recommendations for improving the organizational and technical reliability of planned solutions in the conditions of system risk at the stage of preparation and the main phase of construction of large industrial complexes, such as a nuclear power plant (NPP).
The system analysis carried out by the author forms the basis for methodology recommendations on the selection of a rational option of work plan for the construction of a technically complex industrial facility. The conclusions are made on the basis of the development by the author of his own simulation model of risk analysis using a modern approach to the application of automated systems for scheduling production processes of NPP project implementation, including at the international intergovernmental level.


The research paper characterizes theoretical methods and practical recommendations for the development and selection of a rational variant of work organization at the NPP construction site at all stages of the project life cycle. As a basis for selecting the most rational work organization plan, the author proposes to develop and implement a simulation model on the basis of the Membrane Method, which accumulates data for comparative analysis of the results of all project systems. The essence of this Membrane model is described below.


The paper presents the main requirements to the technical specification for the domestic development of software for processing the data of risk analysis for the NPP construction project realization at each stage of the project life cycle.

Article Details

Section

Domestic and overseas experience

Author Biography

Denis Evgenievich Sezemin, Moscow State University of Civil Engineering (National Research University) (MGSU); Akkuyu Nükleer Anonim Sirketi

Candidate of the degree of Candidate of Technical Sciences; Director for Construction and Production Management

How to Cite

Membrane method in assessment of organizational and technical reliability of NPP construction projects. (2023). Real Estate: Economics, Management, 4, 54-61. https://doi.org/10.22337/2073-8412-2023-4-54-61

References

Альшрайдех М., Енговатов И., Морозенко А. Вопросы управления жизненным циклом АЭС // Энергетическая политика. 2023. № 1 (179). Pp. 56–71. DOI: 10.46920/2409-5516.2023_1179.56 DOI: https://doi.org/10.46920/2409-5516.2023_1179.56

Гаврилов К. А., Красавина Л. Н. Большая Российская Энциклопедия, 2004–2017 гг. URL: https://old.bigenc.ru/economics/text/3510546#:~:text=РИСК%20(франц.%20risque%2C%20от%20итал.,в%20обыденном%20и%20политич.%20дискурсе

Брыкалова С. М., Трифонов В. Ю., Гурьева Е. А. Разработка классификатора рисков как этап успешного риск-менеджмента // Проблемы анализа риска. 2021. Т. 18. № 6. С. 44. DOI: 10.­32686/1812-5220-2021-18-6-40-53

Раменская А. В., Пивоварова К. В. Метод Монте-Карло и инструментальные средства его реализации : методические указания. Оренбург : ОГУ, 2018. 58 с.

Сезёмин Д. Е. Комплексное развитие незастроенных территорий. Опыт строительства АЭС «Аккую» ГК «Росатом» (Турция) // Жилье и городская среда : нац. науч.-практ. конф. с междунар. участием (в смешанном формате) (г. Москва, 20–21 октября 2022 г.).

Грабовый П. Г., Прудько Е. А. Риски в сфере девелопмента // Форум. 2023. № 2 (28). C. 110–114. URL: https://www.elibrary.ru/download/elibrary_50383090_28495156.pdf

Similar Articles

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)